PERMIT NO: 26-0096
|
ON-LINE PERMIT
|
|
|
CLERMONT
City Hall 685 W. Montrose St., FL 34711
|
Schedule inspections through the online system. if you have any problems email us at inspection@clermontfl.org
|
|
PERMIT TYPE
BUILD OUT
|
PERMIT SUB-TYPE
OTHER
|
JOB VALUE 1800000
|
APN 3870739
|
DESCRIPTION
BUILD OUT FOR ORLANDO HEALTH IMAGING CENTER
|
|
|
APPLIED DATE
1/9/2026
|
|
APPROVED DATE
3/2/2026
|
|
ISSUED DATE
3/11/2026
|
|
|
|
PERMIT INFORMATION
|
FEE SUMMARY
|
|
SITE
|
17331 PAGONIA RD CLERMONT, FL 34711
|
|
|
APPLICANT
|
ALBANESE, MICHAEL J
135 W CENTRAL BLVD ORLANDO FL 32801
|
|
|
OWNER
|
RIO DOURADO INVESTMENTS LLC
7901 KINGSPOINTE PKWY STE 10 ORLANDO FL 32819
|
|
|
CONTRACTOR
|
LAMM & COMPANY PARTNERS LLC
968 LAKE BALDWIN LANE ORLANDO FL 32814
|
|
|
| PRE-POWER APPROVAL FOR FIRST 60 DAYS | $100.00 |
| METER FEES | $168.00 |
| ROAD IMPACT FEE COMMERCIAL | $33,574.25 |
| SEWER IMPACT FEE COMMERCIAL-NEW | $18,390.00 |
| WATER IMPACT FEES COMMERCIAL-NEW | $3,900.00 |
| COMMERCIAL ALTERATIONS/RENO AND SHELL ONLY | $761.35 |
| COMMERCIAL ALTERATIONS/RENO AND SHELL ONLY | $1,522.69 |
| ELECTRICAL PERMIT FEES SQ FT | $287.30 |
| FIRE IMPACT COMM OFFICE SQ FT | $4,384.20 |
| IMPACT ADMIN FEE | $100.00 |
| MECHANICAL PERMIT FEES | $287.30 |
| METER FEES | $1,209.00 |
| POLICE IMPACT COMMERCIAL OFFICE SQ FT | $1,505.45 |
| ROAD IMPACT FEE COMMERCIAL | $22,971.25 |
| SEWER IMPACT FEE COMMERCIAL-NEW | $30,650.00 |
| STATE ADMIN AND INSPEC | $60.12 |
| STATE SURCHARGE | $40.08 |
| WATER IMPACT FEES COMMERCIAL-NEW | $6,500.00 |
| ZONING CLEARANCE 100 | $100.00 |
| ELECTRICAL PERMIT FEES SQ FT | $287.30 |
| PLUMBING PERMIT FEES | $287.30 |
| MODIFYING CONSTRUCTION PLANS AFTER PERMI | $85.00 |
| MODIFYING CONSTRUCTION PLANS AFTER PERMI | $85.00 |
| MODIFYING CONSTRUCTION PLANS AFTER PERMI | $85.00 |
| FIRE REVIEW FEE | $574.60 |
| FIRE RESUBMITTAL OF CONSTRUCTION PLANS | $88.00 |
| FIRE RESUBMITTAL OF CONSTRUCTION PLANS | $88.00 |
| FIRE TECHNOLOGY FEE | $68.95 |
| Total Fees Charged: | $128,160.14 |
|
|
|
|
|
|
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT F.S. 713.135
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
INSPECTION SUMMARY
|
| ______ NOTICE OF COMMENCEME |
| ______ UNDERGROUND PLUMBING |
| ______ UNDERGROUND ELECTRIC |
| ______ MONO SLAB |
| ______ MONO SLAB |
| ______ PRE POWER |
| ______ PRE POWER |
| ______ FOOTER/FOUNDATION |
| ______ FRAMING |
| ______ ELECTRIC ROUGH |
| ______ TEMPORARY POLE |
| ______ PRE POWER |
| ______ ROUGH PLUMBING |
| ______ INSULATION ROUGH |
| ______ ROUGH PLUMBING |
| ______ UNDERGROUND ELECTRIC |
| ______ ELECTRIC ROUGH |
| ______ INSULATION ROUGH |
| ______ FRAMING |
| ______ INSULATION ROUGH |
| ______ FRAMING |
| ______ ROUGH MECHANICAL |
| ______ ROUGH MECHANICAL |
| ______ FRAMING |
| ______ ROUGH MECHANICAL |
| ______ ELECTRIC ROUGH |
| ______ ELECTRIC ROUGH |
| ______ FRAMING |
| ______ DRYWALL |
| ______ UNDERGROUND ELECTRIC |
| ______ FRAMING |
| ______ FRAMING |
| ______ ROUGH MECHANICAL |
| ______ FOOTER/FOUNDATION |
| ______ PRE POWER |
| ______ FRAMING |
| ______ ABOVE CEILING |
| ______ ABOVE CEILING |
| ______ LOW VOLTAGE ROUGH |
| ______ FIRE-ABOVE CEILING |
| ______ ROUGH PLUMBING |
| ______ ELECTRIC ROUGH |
| ______ ABOVE CEILING |
| ______ FRAMING |
| ______ LATH |
| ______ FIRE FINAL |
| ______ ELECTRIC FINAL |
| ______ MECHANICAL FINAL |
| ______ PLUMBING FINAL |
| ______ LOW VOLTAGE FINAL |
| ______ FINAL BUILDING |
| ______ FIRE CONSULTATION |
| ______ FIRE PENETRATION |
| ______ ROUGH PLUMBING |
| ______ FRAMING |
| ______ ELECTRIC ROUGH |
| ______ ABOVE CEILING |
| ______ FRAMING |
|
|
|
|
|