PERMIT TYPE
  STRUCTURES OTHER BLDG

PERMIT SUB-TYPE
    

JOB VALUE     550000
APN     3540646
DESCRIPTION
    TWO TEMP ENTRANCES FOR NEW BED TOWER PROJECT: SOUTH LAKE HOS
APPLIED DATE
6/2/2021

APPROVED DATE
8/12/2021

ISSUED DATE
8/12/2021
 
Seal    
 
    PERMIT INFORMATION
FEE SUMMARY
    SITE 1900 DON WICKHAM DR CLERMONT F
CLERMONT, FL 34711

    APPLICANT THE ROBINS & MORTON GROUP (ADAMS)
423 S KELLER RD SUITE 200
ORLANDO FL 32810

    OWNER SOUTH LAKE MEMORIAL HOSPITAL
1099 CITRUS TOWER BLVD
CLERMONT FL 34711

    CONTRACTOR THE ROBINS & MORTON GROUP (ADAMS)
423 S KELLER RD SUITE 200
ORLANDO FL 32810
COMMERCIAL BUILDING PERMIT$1,000.00
FIRE REVIEW FEE$164.00
ELECTRICAL PERMIT FEES SQ FT$100.00
MECHANICAL PERMIT FEES$100.00
PLUMBING PERMIT FEES$100.00
STATE ADMIN AND INSPEC$21.96
STATE SURCHARGE$14.64
ZONING CLEARANCE 100$100.00
FIRE RESUBMITTAL OF CONSTRUCTION PLANS$85.00
Total Fees Charged:$1,685.60
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT F.S. 713.135




:


DATE    ____________
INSPECTION SUMMARY

______  FIREWALL FIRE
______  FIRE-ABOVE CEILING
______  FIRE PENETRATION
______  FIRE FINAL
______  FIRE CONSULTATION
______  FOOTER/FOUNDATION
______  FOOTER/FOUNDATION
______  FOOTER/FOUNDATION
______  FOOTER/FOUNDATION
______  FOOTER/FOUNDATION
______  FOOTER/FOUNDATION
______  STEM WALL FILL
______  STEM WALL FILL
______  FOOTER/FOUNDATION
______  FOOTER/FOUNDATION
______  FRAMING
______  FOOTER/FOUNDATION
______  FIREWALL FRAME-BLDG
______  FRAMING
______  ROUGH MECHANICAL
______  ROUGH MECHANICAL
______  FINAL ALL
______  FIRE FINAL
______  LANDSCAPING (COMM)
______  PRE POWER
______  PUBLIC WORKS (COMM)
______  COLUMNS INSPECTIONS
______  DRYWALL
______  ELECTRIC FINAL
______  ELECTRIC ROUGH
______  FINAL IRRIGATION
______  FIREWALL 1ST LAYER-BLDG
______  FIREWALL FINAL-BLDG
______  FIREWALL PENETRATION-BLDG
______  INSULATION FINAL
______  INSULATION ROUGH
______  LATH
______  MONO SLAB
______  PRE SLAB INSPECTION
______  SLAB
______  STRAPPING/DOOR BUCK
______  TERMITE CERTIFICATE
______  FIRE-ABOVE CEILING
______  FIRE PENETRATION
______  FIRE CONSULTATION
______  NOTICE OF COMMENCEME
______  LOW VOLTAGE ROUGH
______  FOOTER/FOUNDATION
______  FRAMING