PERMIT NO: 21-5219
|
ON-LINE PERMIT
|
|
CLERMONT
City Hall 685 W. Montrose St., FL 34711
|
Schedule inspections through the online system. if you have any problems email us at inspection@clermontfl.org
|
|
PERMIT TYPE
SINGLE FAMILY DETACHED
|
PERMIT SUB-TYPE
|
JOB VALUE 130000
|
APN 1619181
|
DESCRIPTION
New Construction (SFR)
|
|
APPLIED DATE
11/22/2021
|
APPROVED DATE
3/24/2022
|
ISSUED DATE
4/1/2022
|
|
|
PERMIT INFORMATION
|
FEE SUMMARY
|
SITE
|
201 NORTH DISSTON AVE CLERMONT FL CLERMONT, FL 34711
|
|
APPLICANT
|
XCLUSIVE CREATION CORP
745 S. Kirkman Rd Suite# 755 ORLANDO FL 3281132811
|
|
OWNER
|
PIRES RIBEIRO INVESTMENTS LLC
7901 KINGSPOINTE PKWY STE 15 ORLANDO FL 32819
|
|
CONTRACTOR
|
XCLUSIVE CREATION CORP
745 S. Kirkman Rd Suite# 755 ORLANDO FL 32811
|
|
|
FINAL BMEP 04/23/2024 AZ | $105.00 |
IMPACT ADMIN FEE | $100.00 |
IRRIGATION FEE | $75.00 |
METER FEES | $872.00 |
ELECTRICAL PERMIT FEES SQ FT | $120.55 |
MECHANICAL PERMIT FEES | $120.55 |
PLUMBING PERMIT FEES | $120.55 |
PARKS AND RECREATION IMPACT FEE | $3,177.00 |
RESIDENTIAL BUILDING PERMIT | $843.85 |
STATE ADMIN AND INSPEC | $18.08 |
STATE SURCHARGE | $12.06 |
ZONING CLEARANCE | $45.00 |
CITY DRIVE/SIDEWALK 08/25/2023 EM | $105.00 |
MODIFYING CONSTRUCTION PLANS AFTER PERMI | $85.00 |
FOOTER/FOUNDATION 08/26/2022 TM | $105.00 |
CHANGE OF SUB CONTRACTOR | $52.00 |
FRAMING 12/14/2022 TM | $105.00 |
ELECTRICAL PERMIT FEES SQ FT | $12.06 |
MECHANICAL PERMIT FEES | $12.06 |
PLUMBING PERMIT FEES | $12.06 |
RESIDENTIAL BUILDING PERMIT | $84.39 |
STATE ADMIN AND INSPEC | $2.00 |
STATE SURCHARGE | $2.00 |
FIRE IMPACT FEE RESIDENTIAL | $592.00 |
LIBRARY IMPACT FEE SINGLE | $191.00 |
POLICE IMPACT FEE RESIDENTIAL SINGLE | $489.00 |
ROAD IMPACT FEE - SINGLE RESIDENTIAL | $2,706.00 |
SCHOOL IMPACT FEE | $8,927.00 |
SEWER IMPACT FEE RESIDENTIAL | $4,402.00 |
WATER IMPACT FEE RESIDENTIAL | $2,720.00 |
METER INSTALL-PUBLIC SVS 05/18/2023 LA | $105.00 |
FINAL BMEP 10/05/2023 LS | $105.00 |
FRAMING 12/09/2022 RH | $105.00 |
FRAMING 12/19/2022 RH | $105.00 |
ROUGH MEP 12/28/2022 RH | $105.00 |
UNDERGROUND ELECTRIC 09/20/2022 RS | $105.00 |
Total Fees Charged: | $26,843.21 |
|
|
|
|
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT F.S. 713.135
|
|
|
|
|
|
|
|
|
INSPECTION SUMMARY
|
______ NOTICE OF COMMENCEME |
______ UNDERGROUND PLUMBING |
______ FOOTING ELECTRIC BONDING |
______ FOOTER/FOUNDATION |
______ FOOTER/FOUNDATION |
______ FOOTER/FOUNDATION |
______ FORM BOARD SURVEY |
______ UNDERGROUND ELECTRIC |
______ UNDERGROUND ELECTRIC |
______ MONO SLAB |
______ LINTEL |
______ LINTEL |
______ SHEATHING-WALL NAIL |
______ SHEATHING-ROOF NAIL |
______ FRAMING |
______ FRAMING |
______ FRAMING |
______ FRAMING |
______ ROUGH MECHANICAL |
______ ROUGH MEP |
______ ROUGH PLUMBING |
______ ROUGH MECHANICAL |
______ ROOF DRY-IN/FLASHING |
______ FRAMING |
______ FRAMING |
______ ROUGH MEP |
______ WINDOW DOOR BUCK |
______ INSULATION ROUGH |
______ RATED DRYWALL |
______ LATH |
______ INSULATION ROUGH |
______ TUG INSPECTION |
______ INSULATION ROUGH |
______ METER INSTALL-PUBLIC SVS |
______ CITY SEWER |
______ BLOWER DOOR TEST REPORT |
______ CITY DRIVE/SIDEWALK |
______ IN PROGRESS-SOFFIT COVERING |
______ CITY DRIVE/SIDEWALK |
______ FINAL BMEP |
______ CONSULTATION-BLDG |
______ PRE POWER |
______ PRE POWER |
______ FINAL BMEP |
______ CITY FINAL |
______ FINAL GAS |
______ FIREWALL FINAL-BLDG |
______ ROUGH GAS |
______ SLAB ELECTRIC BONDING |
______ TEMPORARY POLE |
______ IN PROGRESS-BALCONY MOISTURE BARRIER |
______ IN PROGRESS-EXT WALL COVERING |
______ IN PROGRESS-EXTERIOR VENEER |
______ STEM WALL FILL |
______ STEMWALL FOOTER |
______ SEWER (BLDG) |
______ MONO SLAB |
______ MONO SLAB |
______ PRE POWER |
______ FINAL BMEP |
|
|
|
|