PERMIT NO: 24-2553
|
ON-LINE PERMIT
|
|
CLERMONT
City Hall 685 W. Montrose St., FL 34711
|
Schedule inspections through the online system. if you have any problems email us at inspection@clermontfl.org
|
|
PERMIT TYPE
RESIDENTAL ALTERATION
|
PERMIT SUB-TYPE
|
JOB VALUE 80000
|
APN 2795433
|
DESCRIPTION
INTERIOR REMODEL (NEW LAYOUT, EXTERIOR WALL REPLACEMENT, REW
|
|
APPLIED DATE
6/5/2024
|
APPROVED DATE
7/12/2024
|
ISSUED DATE
7/12/2024
|
|
|
PERMIT INFORMATION
|
FEE SUMMARY
|
SITE
|
2285 S LAKESHORE DR CLERMONT, FL 34711
|
|
APPLICANT
|
ARIAS MARIA & JORGE M MONTOYA
2285 S LAKESHORE DR CLERMONT FL 34711
|
|
OWNER
|
ARIAS MARIA & JORGE M MONTOYA
2285 S LAKESHORE DR CLERMONT FL 34711
|
|
|
|
PRE POWER 01/28/2025 AZ | $105.00 |
RESIDENTIAL ALTERATIONS/RENOVATIONS | $976.60 |
ZONING CLEARANCE | $45.00 |
STATE ADMIN AND INSPEC | $25.64 |
STATE SURCHARGE | $17.09 |
ELECTRICAL PERMIT FEES SQ FT | $244.15 |
PLUMBING PERMIT FEES | $244.15 |
MECHANICAL PERMIT FEES | $244.15 |
Total Fees Charged: | $1,901.78 |
|
|
|
|
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT F.S. 713.135
|
|
|
|
|
|
|
|
|
INSPECTION SUMMARY
|
______ NOTICE OF COMMENCEME |
______ LINTEL |
______ FOOTER/FOUNDATION |
______ SHEATHING-WALL NAIL |
______ ELECTRIC ROUGH |
______ ROUGH MECHANICAL |
______ ROUGH MECHANICAL |
______ MECHANICAL FINAL |
______ UNDERGROUND PLUMBING |
______ UNDERGROUND PLUMBING |
______ ROUGH PLUMBING |
______ ROUGH PLUMBING |
______ UNDERGROUND PLUMBING |
______ 2ND ROUGH PLUMBING |
______ FRAMING |
______ WINDOW DOOR BUCK |
______ FRAMING |
______ ROUGH PLUMBING |
______ ROUGH PLUMBING |
______ FRAMING |
______ WINDOW DOOR BUCK |
______ WINDOW DOOR BUCK |
______ FRAMING |
______ LATH |
______ INSULATION FINAL |
______ PRE POWER |
______ PRE POWER |
______ MECHANICAL FINAL |
______ ROUGH GAS |
______ FINAL GAS |
______ MECHANICAL FINAL |
______ ELECTRIC FINAL |
______ FINAL GAS |
______ ELECTRIC FINAL |
______ MECHANICAL FINAL |
______ FINAL BUILDING ** |
______ BLOWER DOOR TEST REPORT |
______ CONSULTATION-BLDG |
______ FINAL BUILDING |
______ IN PROGRESS |
______ INSULATION ROUGH |
______ MONO SLAB |
______ PLUMBING FINAL |
______ PRE CONSTRUCTION MEETING-BLDG |
______ PRE SLAB INSPECTION |
______ STRAPPING/DOOR BUCK |
______ UNDERGROUND ELECTRIC |
______ WINDOW/DOOR |
______ LINTEL |
______ FOOTER/FOUNDATION |
______ ELECTRIC ROUGH |
______ UNDERGROUND PLUMBING |
______ 2ND ROUGH PLUMBING |
______ ROUGH GAS |
______ MECHANICAL FINAL |
______ ELECTRIC FINAL |
______ FINAL GAS |
|
|
|
|