PERMIT NO:  24-3903
ON-LINE PERMIT
   CLERMONT
   City Hall 685 W. Montrose St., FL 34711

Schedule inspections through the online system. if you have any problems email us at inspection@clermontfl.org




PERMIT TYPE
  STORES/CUSTOMER SERVICE

PERMIT SUB-TYPE
    

JOB VALUE     1400000
APN     3938032
DESCRIPTION
    NEW CONSTRUCTION WHITE CASTLE W/ DRIVE-THRU & EXTERIOR PATIO
APPLIED DATE
8/29/2024

APPROVED DATE
3/10/2025

ISSUED DATE
3/12/2025
 
Seal    
 
    PERMIT INFORMATION
FEE SUMMARY
    SITE 4551 COLLINA TERRACE
CLERMONT, FL 34711

    APPLICANT CUHACI PETERSON ARCHITECTS
2600 MAITLAND CENTER PKWY
MAITLAND FL 32751

    OWNER PROFESSIONAL RESOURCE DEVELOPM
270 W PLANT ST
WINTER GARDEN FL 34787

    CONTRACTOR STANSELL PROPERTIES & DEVELOPMENT LLC
11607 PROSPECT ROAD
ODESSA FL 33556
COMMERCIAL BUILDING PERMIT$853.30
ADDRESS FOR FOR LAKE COUNTY$20.00
COMMERCIAL BUILDING PERMIT$853.30
ELECTRICAL PERMIT FEES SQ FT$161.00
FIRE IMPACT COMM RETAIL OTHER$7,399.56
IMPACT ADMIN FEE$100.00
MECHANICAL PERMIT FEES$161.00
METER FEES$1,377.00
PLUMBING PERMIT FEES$161.00
POLICE IMPACT COMM RETAIL OTHER$2,540.58
ROAD IMPACT FEE COMMERCIAL$97,343.82
SEWER IMPACT FEE COMMERCIAL-NEW$49,040.00
SITE INSPECTION FEE$1,307.00
STATE ADMIN AND INSPEC$47.33
STATE SURCHARGE$31.56
WATER IMPACT FEES COMMERCIAL-NEW$10,400.00
ZONING CLEARANCE 100$100.00
ELECTRICAL PERMIT FEES SQ FT$161.00
GAS PIPING/FIXTURES$161.00
FIRE REVIEW FEE$322.00
EXPEDITED PLAN REVIEW-BLDG$900.00
FIRE EXPEDITED PLAN REVIEW FEE$528.00
FOOTER/FOUNDATION 03/27/2025 LS$105.00
FIRE REVIEW FEE$322.00
FIRE TECHNOLOGY FEE$19.32
Total Fees Charged:$174,414.77
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT F.S. 713.135




:


DATE    ____________
INSPECTION SUMMARY

______  FOOTING ELECTRIC BONDING
______  FOOTER/FOUNDATION
______  FOOTING ELECTRIC BONDING
______  FOOTER/FOUNDATION
______  STEM WALL FILL
______  UNDERGROUND PLUMBING
______  FOOTER/FOUNDATION
______  UNDERGROUND ELECTRIC
______  SLAB
______  MASONRY WALL
______  SLAB
______  MASONRY WALL
______  ROOF DECKING (COMM)
______  IN PROGRESS-EXT WALL COVERING
______  ELECTRIC ROUGH
______  ROUGH MECHANICAL
______  IN PROGRESS-EXT WALL COVERING
______  IN PROGRESS-EXTERIOR VENEER
______  FIRE CONSULTATION
______  PUBLIC WORKS (COMM)
______  LANDSCAPING (COMM)
______  FIRE FINAL
______  FIRE-ABOVE CEILING
______  DUCT WRAP
______  MECHANICAL FINAL
______  FIRE PENETRATION
______  2ND ROUGH PLUMBING
______  ABOVE CEILING
______  BLOWER DOOR TEST REPORT
______  BUILIDING-LIFE SAFETY
______  DRYWALL
______  DUCT WRAP
______  EIFS
______  ELECTRIC FINAL
______  FINAL BUILDING
______  FINAL GAS
______  FIREWALL 1ST LAYER-BLDG
______  FIREWALL 2ND LAYER-BLDG
______  FIREWALL PENETRATION-BLDG
______  FORM BOARD SURVEY
______  FRAMING
______  IN PROGRESS-SOFFIT COVERING
______  INSULATION FINAL
______  INSULATION ROUGH
______  KITCHEN HOOD CONTAIN-BLDG
______  KITCHEN HOOD LIGHT-BLDG
______  KITCHEN HOOD SMK TST BLDG
______  KITCHEN HOOD-BLDG
______  LATH
______  LINTEL
______  LOW VOLTAGE FINAL
______  LOW VOLTAGE ROUGH
______  MECHANICAL FINAL
______  METER INSTALL-PUBLIC SVS
______  OPEN TRENCH PL/EL
______  PLUMBING FINAL
______  RATED DRYWALL
______  ROOF DRY-IN/FLASHING
______  ROOF FINAL
______  ROOF SECONDARY BARRI
______  ROUGH GAS
______  ROUGH MECHANICAL
______  SEWER (BLDG)
______  SLAB ELECTRIC BONDING
______  STRAPPING/DOOR BUCK
______  TERMITE CERTIFICATE
______  UNDER/ABOVE WTR STR
______  WINDOW/DOOR
______  ROUGH PLUMBING
______  NOTICE OF COMMENCEME
______  ROOF DECKING (COMM)
______  ELECTRIC ROUGH
______  ROUGH MECHANICAL
______  IN PROGRESS-EXT WALL COVERING
______  COLUMNS INSPECTIONS