PERMIT NO: 24-4652
|
ON-LINE PERMIT
|
|
CLERMONT
City Hall 685 W. Montrose St., FL 34711
|
Schedule inspections through the online system. if you have any problems email us at inspection@clermontfl.org
|
|
PERMIT TYPE
RESIDENTIAL ADDITIONS
|
PERMIT SUB-TYPE
|
JOB VALUE 357359
|
APN 1714656
|
DESCRIPTION
PARTIAL DEMO & NEW 2 STORY ADDITION (GARAGE, 2 BEDROOMS, BAT
|
|
APPLIED DATE
10/17/2024
|
APPROVED DATE
11/8/2024
|
ISSUED DATE
11/8/2024
|
|
|
PERMIT INFORMATION
|
FEE SUMMARY
|
SITE
|
168 E LAKESHORE DR CLERMONT, FL 34711
|
|
APPLICANT
|
LAKE CONSTRUCTION AND DEV - STEVEN
211 CITRUS TOWER BLVD CLERMONT FL 34711
|
|
OWNER
|
PHILLIPS JAMES C
168 E LAKESHORE DR CLERMONT FL 34711
|
|
CONTRACTOR
|
LAKE CONSTRUCTION AND DEV - STEVEN
211 CITRUS TOWER BLVD CLERMONT FL 34711
|
|
|
RESIDENTIAL ALTERATIONS/RENOVATIONS | $322.00 |
STATE ADMIN AND INSPEC | $8.45 |
STATE SURCHARGE | $5.64 |
ZONING CLEARANCE | $45.00 |
ELECTRICAL PERMIT FEES SQ FT | $80.50 |
MECHANICAL PERMIT FEES | $80.50 |
PARKS AND RECREATION IMPACT FEE | $1,503.00 |
PLUMBING PERMIT FEES | $80.50 |
PLUMBING FINAL 06/30/2025 JWA | $105.00 |
Total Fees Charged: | $2,230.59 |
|
|
|
|
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT F.S. 713.135
|
|
|
|
|
|
|
|
|
INSPECTION SUMMARY
|
______ ROUGH PLUMBING |
______ NOTICE OF COMMENCEME |
______ MONO SLAB |
______ MONO SLAB |
______ FOOTER/FOUNDATION |
______ LINTEL |
______ SHEATHING-WALL NAIL |
______ SHEATHING-ROOF NAIL |
______ SHEATHING-ROOF NAIL |
______ SHEATHING-WALL NAIL |
______ ROOF DRY-IN/FLASHING |
______ WALL-DRY IN |
______ WINDOW DOOR BUCK |
______ 2ND ROUGH PLUMBING |
______ FRAMING |
______ ELECTRIC ROUGH |
______ ROUGH MECHANICAL |
______ FRAMING |
______ WINDOW/DOOR |
______ WINDOW DOOR BUCK |
______ INSULATION ROUGH |
______ INSULATION ROUGH |
______ DRYWALL |
______ LATH |
______ IN PROGRESS |
______ INSULATION FINAL |
______ IN PROGRESS |
______ PRE POWER |
______ PRE POWER |
______ ROOF FINAL |
______ MECHANICAL FINAL |
______ ELECTRIC FINAL |
______ ELECTRIC FINAL |
______ MECHANICAL FINAL |
______ PLUMBING FINAL |
______ FINAL BUILDING |
______ PLUMBING FINAL |
|
|
|
|