PERMIT NO: 24-4933
|
ON-LINE PERMIT
|
|
CLERMONT
City Hall 685 W. Montrose St., FL 34711
|
Schedule inspections through the online system. if you have any problems email us at inspection@clermontfl.org
|
|
PERMIT TYPE
BUILD OUT
|
PERMIT SUB-TYPE
RESTAURANT
|
JOB VALUE 109000
|
APN 3937653
|
DESCRIPTION
RESTAURANT BUILD OUT CROSS RIDGE EXCHANGE BLDG 2-BLOOMSPHERE
|
|
APPLIED DATE
11/1/2024
|
APPROVED DATE
1/6/2025
|
ISSUED DATE
1/6/2025
|
|
|
PERMIT INFORMATION
|
FEE SUMMARY
|
SITE
|
2633 S US HIGHWAY 27 STE 102 CLERMONT, FL 34711
|
|
APPLICANT
|
GREENLOGIC LLC
1605 HEMPEL AVENUE WINDERMERE FL 34786
|
|
OWNER
|
JDS 13 INVESTMENTS LLC
1007 CELADON ST OAKLAND FL 34787
|
|
CONTRACTOR
|
GREENLOGIC LLC
1605 HEMPEL AVENUE WINDERMERE FL 34786
|
|
|
COMMERCIAL ALTERATIONS/RENO AND SHELL ONLY | $537.69 |
FIRE BUILD OUT/REMODEL | $202.90 |
ELECTRICAL PERMIT FEES SQ FT | $101.45 |
STATE ADMIN AND INSPEC | $15.67 |
STATE SURCHARGE | $10.45 |
ZONING CLEARANCE | $45.00 |
ELECTRICAL PERMIT FEES SQ FT | $101.45 |
GAS PIPING/FIXTURES | $101.45 |
MECHANICAL PERMIT FEES | $101.45 |
PLUMBING PERMIT FEES | $101.45 |
ROAD IMPACT FEE COMMERCIAL | $16,093.84 |
MODIFYING CONSTRUCTION PLANS AFTER PERMI | $85.00 |
FIRE RESUBMITTAL OF CONSTRUCTION PLANS | $88.00 |
FIRE TECHNOLOGY FEE | $24.35 |
FIRE RESUBMITTAL OF CONSTRUCTION PLANS | $88.00 |
Total Fees Charged: | $17,698.15 |
|
|
|
|
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT F.S. 713.135
|
|
|
|
|
|
|
|
|
INSPECTION SUMMARY
|
______ NOTICE OF COMMENCEME |
______ UNDERGROUND PLUMBING |
______ UNDERGROUND ELECTRIC |
______ UNDERGROUND PLUMBING |
______ UNDERGROUND PLUMBING |
______ SLAB |
______ SLAB |
______ FRAMING |
______ ELECTRIC ROUGH |
______ 2ND ROUGH PLUMBING |
______ MASONRY WALL |
______ ROUGH GAS |
______ ROUGH MECHANICAL |
______ MASONRY WALL |
______ ROUGH GAS |
______ ELECTRIC ROUGH |
______ ROUGH GAS |
______ FINAL GAS |
______ DUCT WRAP |
______ ROUGH MECHANICAL |
______ FIRE INSULATION WRAP |
______ BUILIDING-LIFE SAFETY |
______ FIRE FINAL |
______ FIRE PENETRATION |
______ FIRE-ABOVE CEILING |
______ ABOVE CEILING |
______ ELECTRIC FINAL |
______ LOW VOLTAGE FINAL |
______ LOW VOLTAGE ROUGH |
______ MECHANICAL FINAL |
______ PLUMBING FINAL |
______ ABOVE CEILING |
______ FINAL BUILDING |
______ FINAL GAS |
______ DUCT WRAP |
______ ROUGH MECHANICAL |
|
|
|
|