PERMIT NO: 26-1569
|
ON-LINE PERMIT
|
|
|
CLERMONT
City Hall 685 W. Montrose St., FL 34711
|
Schedule inspections through the online system. if you have any problems email us at inspection@clermontfl.org
|
|
PERMIT TYPE
SINGLE FAMILY DETACHED
|
PERMIT SUB-TYPE
|
JOB VALUE 466186
|
APN 3957875
|
DESCRIPTION
SFR - MCKINNON GROVES PHASE 1 LOT 26 WITH GAS
|
|
|
APPLIED DATE
4/13/2026
|
|
APPROVED DATE
4/29/2026
|
|
ISSUED DATE
4/29/2026
|
|
|
|
PERMIT INFORMATION
|
FEE SUMMARY
|
|
SITE
|
11333 BOURBON ROSE CIR WINTER GARDEN, FL 34787
|
|
|
APPLICANT
|
TAYLOR MORRISON OF FLORIDA, INC
2600 Lake Lucien Drive, Suite 350 Maitland FL 32751
|
|
|
OWNER
|
KL LB BUY 5 LLC
111 WEST 33rd ST NEW YORK NY 10120
|
|
|
CONTRACTOR
|
TAYLOR MORRISON OF FLORIDA, INC
2600 Lake Lucien Drive, Suite 350 Maitland FL 32751
|
|
|
| IMPACT ADMIN FEE | $100.00 |
| FIRE IMPACT FEE RESIDENTIAL | $1,370.00 |
| LIBRARY IMPACT FEE SINGLE | $263.00 |
| ROAD IMPACT FEE - SINGLE RESIDENTIAL | $4,960.00 |
| SCHOOL IMPACT FEE | $0.00 |
| METER FOR SFR | $542.00 |
| ELECTRICAL PERMIT FEES SQ FT | $224.70 |
| GAS PIPING/FIXTURES | $224.70 |
| MECHANICAL PERMIT FEES | $224.70 |
| PLUMBING PERMIT FEES | $224.70 |
| PARKS AND RECREATION IMPACT FEE | $3,736.00 |
| POLICE IMPACT FEE RESIDENTIAL SINGLE | $580.00 |
| RESIDENTIAL BUILDING PERMIT | $1,797.60 |
| SEWER IMPACT FEE RESIDENTIAL | $4,830.00 |
| STATE ADMIN AND INSPEC | $40.45 |
| STATE SURCHARGE | $26.96 |
| WATER IMPACT FEE RESIDENTIAL | $2,836.00 |
| ZONING CLEARANCE | $45.00 |
| SHEATHING-ROOF NAIL 06/22/2026 CKAN | $105.00 |
| FRAMING 07/27/2026 JJM | $105.00 |
| Total Fees Charged: | $22,235.81 |
|
|
|
|
|
|
WARNING TO OWNER: YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE RECORDING YOUR NOTICE OF COMMENCEMENT F.S. 713.135
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
INSPECTION SUMMARY
|
| ______ FORM BOARD SURVEY |
| ______ UNDERGROUND PLUMBING |
| ______ SEWER (BLDG) |
| ______ CITY SEWER |
| ______ SLAB |
| ______ LINTEL |
| ______ SHEATHING-WALL NAIL |
| ______ SHEATHING-ROOF NAIL |
| ______ SHEATHING-WALL NAIL |
| ______ TUG INSPECTION |
| ______ SHEATHING-ROOF NAIL |
| ______ WINDOW DOOR BUCK |
| ______ ROOF DRY-IN/FLASHING |
| ______ ROUGH PLUMBING |
| ______ ROUGH MECHANICAL |
| ______ ROUGH GAS |
| ______ ROUGH PLUMBING |
| ______ FRAMING |
| ______ LATH |
| ______ ELECTRIC ROUGH |
| ______ FRAMING |
| ______ FRAMING |
| ______ INSULATION ROUGH |
| ______ CITY DRIVE/SIDEWALK |
| ______ BLOWER DOOR TEST REPORT |
| ______ CITY FINAL |
| ______ FOOTER/FOUNDATION |
| ______ FOOTING ELECTRIC BONDING |
| ______ IN PROGRESS-SOFFIT COVERING |
| ______ SEWER (BLDG) |
| ______ SLAB ELECTRIC BONDING |
| ______ TERMITE CERTIFICATE |
| ______ ELECTRIC FINAL |
| ______ FINAL BUILDING |
| ______ INSULATION FINAL |
| ______ MECHANICAL FINAL |
| ______ PLUMBING FINAL |
| ______ NOTICE OF COMMENCEME |
| ______ MONO SLAB |
| ______ FINAL GAS |
| ______ IN PROGRESS-EXT WALL COVERING |
| ______ IN PROGRESS-EXTERIOR VENEER |
| ______ PRE POWER |
| ______ ROOF FINAL |
| ______ UNDERGROUND PLUMBING |
| ______ TERMITE CERTIFICATE |
| ______ UNDERGROUND ELECTRIC |
| ______ SHEATHING-ROOF NAIL |
| ______ FRAMING |
|
|
|
|
|