Notes:
6/18/2018 3:19:45 PM
THIS PERMIT WAS SUBMITTED PRIOR TO SITE PLAN SUBMITTAL, THEREFORE, MELISSA ORTIZ WITH EDWARDS CONSTRUCTION WAS INFORMED THAT THIS IS NOT CONSIDERED TO BE SUBMITTED UNTIL WE RECEIVE THE SITE PLAN SUBMITTAL.
THEY PAID FOR PERMITS 18-0139 AND 18-0140 WITH A CHECK WITH AN OVERAGE OF $168.10 THAT IS BEING APPLIED TO THE PREPAID PLAN REVIEW FEE FOR THIS PERMIT.
10/5/2018 3:33:51 PM
REVISION SUBMITTED 10/5/2018
HE INSERTED SHEETS IN TWO OF 3 PLANS AND PUT 3RD SET INSIDE FILE COPY ROLL
10/30/2018 8:41:36 AM
RESUBMITTAL TO CORRECT NOTED DEFICIENCIES REC 10/29/18
11/7/2018 12:02:30 PM
11/07/18
emailed letter regarding no leasing or renting of clubhouse.
11/15/2018 4:14:36 PM
2" water meter required per Mark Ciurzynski with Edwards
11/15/2018 4:14:50 PM
no road impat fees required per mary harris
12/13/2018 1:01:31 PM
LETTER ON FILE TO DELAY PAYMENT OF IMPACT FEES UNTIL PRIOR TO CO RECEIVED 12/13/2018
12/13/2018 1:26:44 PM
IMPACT FEES TO BE PAID PRIOR TO CO
POLICE $1683.75
FIRE $2544.58
WATER $9060.00
SEWER $31,995.00
2/18/2019 10:48:14 AM
REVISION WAS SUBMITTED ON 01-25-19
6/18/2019 10:51:02 AM
REVISIONS SUBMITTED ON 06-18-19 FOR ELECTRICAL PANEL IN POOL EQUIP CORRAL AND SITE LIGHTING ADDED @ RAMP